Water Transfer

 
  1. Callaghan Trunkmain Upgrade

    Location: Callaghan

    Timeframe: Works completed by November 2011

    The Callaghan Trunkmain Upgrade is part of Hunter Water’s ongoing program of works to improve and enhance the performance of the water network.
  2. Cardiff South Water Pumping Station

    Cardiff South Water Pumping Station Upgrade

    Location: Cardiff South

    Timeframe: February - June 2012

  3. Fletcher Trunkmain Thumbnail

    Fletcher Trunkmain Upgrade

    Location: Lenaghans Drive, Lenaghan

    Timeframe: Commencing mid Nov 2011

    The Fletcher trunkmain runs from Wallsend Water Pumping Station to Stoney Pinch Reservoir, crossing the Hexham Swamp Wetland between Fletcher and Lenaghans Drive.
  4. Callaghan Trunkmain Upgrade

    Location: Callaghan

    Timeframe: Works completed by November 2011

    The Callaghan Trunkmain Upgrade is part of Hunter Water’s ongoing program of works to improve and enhance the performance of the water network.
  5. Cardiff South Water Pumping Station

    Cardiff South Water Pumping Station Upgrade

    Location: Cardiff South

    Timeframe: February - June 2012

  6. Cessnock Water Supply Upgrade Thumbnail

    Cessnock Water Supply Upgrade

    Location: Cessnock

    Timeframe: 18 months

    In 2006/2007 the Department of Planning’s Lower Hunter Regional Strategy projected additional growth (an increase of 21,000 lots by 2031) around Cessnock.
  7. Stoney Pinch CTGM_thumbnail

    Chichester Trunk Gravity Main Upgrade - Beresfield to Stoney Pinch Reservoir

    Location: John Renshaw Drive

    Timeframe: 12 months

    Hunter Water is currently upgrading a 2.7 km section of the Chichester Trunk Gravity Main between Beresfield and Stoney Pinch Reservoir.
  8. Chichester Gravity Main Thumbnail

    Chichester Trunk Gravity Main Upgrade - Tarro to Shortland

    Location: Tarro and Shortland

    Timeframe: 12 months

    Hunter Water has recently completed construction of an underground section of the Chichester Trunk Gravity Main between Tarro and Shortland to improve regional water security.
  9. Fletcher Trunkmain Thumbnail

    Fletcher Trunkmain Upgrade

    Location: Lenaghans Drive, Lenaghan

    Timeframe: Commencing mid Nov 2011

    The Fletcher trunkmain runs from Wallsend Water Pumping Station to Stoney Pinch Reservoir, crossing the Hexham Swamp Wetland between Fletcher and Lenaghans Drive.
  10. South Wallsend Water Supply Thumbnail

    Macquarie Road Watermain Upgrade

    Location: Macquarie Road, Warners Bay

    Timeframe: 3 months

    Hunter Water plans to construct a new watermain along Macquarie Road between Macquarie Hills and Warners Bay.

Featured Project

View All

Chichester Trunk Gravity Main Upgrade - Beresfield to Stoney Pinch Reservoir

Hunter Water is currently upgrading a 2.7 km section of the Chichester Trunk Gravity Main between Beresfield and Stoney Pinch Reservoir.